Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

In 2015, about what percentage of the population lived in poverty? 2 5.5 14.5 24
What are the two phases of cell destruction common to strokes head traumas and spinal cord injuries?
A triangle has side lengths of 15, 20, and 25. What type of triangle is it?a.) rightb.) equiangularc.) acuted.) obtuse​
Which famous singer is in the picture?​
what is the difference between mordern mode of transport and traditional mode of transport​
explain why HHS workers should not impose their own values on their client while advocating for client needs?
what is the equation of the line?​
Children who are not nominated by their peers either as being liked or as being disliked are categorized as
Mañana yo ___ al museo de arte. A- fui B- ire C- iba D- ve
How do you do this? Please help