Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

the volume of the Box 4 inches wide 2 inches high and 5 in long is
What is the measure of Z if W equals to 116*
how much amendments dose the state of California have?
How many degrees is this?
Which equation represents the hyperbola in general form?
How is an increase in carbon in the atmosphere likely to affect coastal areas such as those in North Carolina?
HELP!!!! Which of the following correctly relates the porosity, permeability and production of a well in an aquifer? a. Increasing porosity and decreasing perm
PLEASE HELP ASAP!!! CORRECT ANSWER ONLY PLEASE!!! I CANNOT RETAKE THIS AND I NEED ALL CORRECT ANSWERS ONLY!!! True or False: Doorbells, scrap yards, and rock co
Please help me that’s would be great and I promise to mark brainlest!!
Transferable skills necessary for successful employment include