In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Which of the following is a characteristic of a nation? a sovereign government a large population a strong economy an official language
What should prewriting help a writer do
During World War I, why was propaganda important for the war efforts?
Roberto says that the opposite of a certain integer is -5. cindy concludes that the opposite of an integer is always negative explain cindy error
975,462 rounded to the nearest hundred thousand
What continent is located south of Europe
You are to give ampicillin 35 mg/kg to a child with a mass of 26 kg. If stock on hand is 250 mg/capsule, how many capsules should be given?
What did Booker T. Washington believe that the best strategy to end racial segregation was for African Americans?
How did building New England towns and cities around a common help colonies develop a diverse economy?
what were the main affirmations of the declaration of the rights of man and the citizen